Middlecave Yard – Mid October 2025

See more of the Middlecave work here!

And here’s mid-October’s update on the Middlecave Yard Demolition and rebuilt.

The site as seen from across Middlecave Road.

The retained outbuilding on the corner of Middlecave Road and Back Lane. No external work appears to have started on these outer walls yet.

Contractor banner on the outbuilding.

The outbuild as seen from the north-west side of the site.

The outbuilding. The concrete ring looks to be the right size to cover the black attenuation tank to the left.

Across the yard from the location of the Middlecave Road entrance gates. The black circular tank appears to be a water attenuation tank as seen on the plan at the bottom.

A closer shot of the water attenuation tank.

Construction equipment and shaped reinforcing bar.

A closer shot of the reinforcing bar.

The site from the west corner. The forms noted last time now have reinforcing bar concreted in.

A close up of the forms with the added reinforcing bar.

The site from Back Lane. At the very bottom you can see ducting for future services.

A closer shot of the service ducting.